The NETWORKDAYS function

Counts the working days (Mon–Fri) between two dates, both included.

In German Excel: NETTOARBEITSTAGE

How to write it

=NETWORKDAYS(start_date, end_date, [holidays])
start_date
The first date.
end_date
The last date.
holidays
Optional. Days off that don’t count.

💡 If the end is before the start, the result is negative.

Try it

How many working days does the design phase take?

A
B
C
D
1
Task
Start
End
Workdays
2
Design
6/2/25
6/13/25
3
Build
6/16/25
7/11/25
4
Test
7/14/25
7/25/25
5
6
Holidays
6/9/25
6/19/25

=NETWORKDAYS(start, end).