ExcelHero

The WORKDAY function

Returns the date a number of working days later (or earlier).

In German Excel: ARBEITSTAG

How to write it

=WORKDAY(start_date, days, [holidays])
start_date
The date to start from.
days
Working days forward, or negative for back.
holidays
Optional. Days off to skip.

💡 Perfect for deadlines like “in 5 working days”.

Try it

Testing has to be done 5 working days after it starts. What is the deadline?

A
B
C
D
1
Task
Start
End
Deadline
2
Design
6/2/25
6/13/25
3
Build
6/16/25
7/11/25
4
Test
7/14/25
7/25/25
5
6
Holidays
6/9/25
6/19/25

=WORKDAY(start, 5) skips the weekend for you.